Old Furnace Road Sidewalks

The South Carolina Department of Transportation (SCDOT) will be constructing sidewalks on Old Furnace Road (S-56) from North Spartanburg Sports Complex entrance (MP 1.45) towards the Boiling Springs Freshman Campus to Mason Road (MP 4.33) near Boiling Springs High School.

Schedule

  • Preliminary Engineering began Autumn 2013 and is scheduled to be complete Summer 2016.
  • Right-of-Way began Spring 2015 and is scheduled to be complete Summer 2016.
  • Construction was completed in 2017.

Updates

June 2015

  • PE is approximately 70% complete.
  • ROW Acquisition will begin Summer 2015.
  • Utility Coordination is underway.
  • Construction Letting is scheduled for Fall 2016.

February 2016

  • PE is approximately 75% complete.
  • ROW Acquisition is 90% complete.
  • Utility Coordination is underway.
  • Construction Letting is scheduled for Fall 2016.

November 2017

  • PE is 100% complete.
  • ROW Acquisition is 100% complete.
  • Construction is substantially complete.