The South Carolina Department of Transportation (SCDOT) will be constructing sidewalks on Old Furnace Road (S-56) from North Spartanburg Sports Complex entrance (MP 1.45) towards the Boiling Springs Freshman Campus to Mason Road (MP 4.33) near Boiling Springs High School.
Schedule
- Preliminary Engineering began Autumn 2013 and is scheduled to be complete Summer 2016.
- Right-of-Way began Spring 2015 and is scheduled to be complete Summer 2016.
- Construction was completed in 2017.
Updates
June 2015
- PE is approximately 70% complete.
- ROW Acquisition will begin Summer 2015.
- Utility Coordination is underway.
- Construction Letting is scheduled for Fall 2016.
February 2016
- PE is approximately 75% complete.
- ROW Acquisition is 90% complete.
- Utility Coordination is underway.
- Construction Letting is scheduled for Fall 2016.
November 2017
- PE is 100% complete.
- ROW Acquisition is 100% complete.
- Construction is substantially complete.